Wellington Close

wellington-header

Welcome to d+b facades ‘construction phase’ page for Wellington Close

GENERAL DESCRIPTION

Three mirrored blocks at Wellington Close, Walton-On-Thames consist of a ten-storey high-rise with adjoining two-storey low-rise, the blocks were originally built in the 1960’s and their construction consists of a concrete frame with curtain wall and brick infills. The three towers are freehold owned and accommodate a total of 132 two-bedroom apartments providing affordable living within the local area of Walton-On-Thames.

The new high quality and non-combustible overcladding system will thermally upgrade the building helping to retain heat during winter cold spells and keep the building cool during summer hot spells this is in addition to providing a modern aesthetically pleasing “brand new” appearance.

PLANNED WORKS

24 Hours

With main contracted works to block A now complete, additional instructed works are all that remain – handrails/ and ground floor doors + screens. Works are underway to gain all statutory approvals prior to proceeding onsite.

Block B’s Support structure is now complete and window installation nears completion. Insulation and fire barriers are installed progressively as panel deliveries arrive and re-roofing works to the tower are underway.

7 Days

Block A, main contracted works are complete with additional instructed items only remaining – ground floor handrails/ ground floor doors + screens/ ground floor rendering/ Tower roof plant room cladding

Block B’s Support structure is now complete and window installation nears completion. Insulation and fire barriers are installed progressively as panel deliveries arrive and re-roofing works to the tower are well underway. Current works underway within balconies are rendering/ window and door installation/ new flooring membrane installation/ new balustrade 1st fix.

28 Days

Block A, main contracted works are complete with additional instructed items only remaining – these are all expected to be complete over the next 4 weeks; ground floor handrails/ ground floor doors + screens/ ground floor rendering/ Tower roof plant room cladding

Block B’s Support structure is now complete and window installation also nears completion. Insulation and fire barriers are installed progressively as panel deliveries arrive and re-roofing works to the tower are in progress. Current works underway within balconies are rendering/ window and door installation/ new flooring membrane installation/ new balustrades.

Overall

Construction works for each tower block is programmed to take 30 weeks with works starting on Block A 01/10/18, works to Blocks B+C will follow completing all construction work by 90 weeks;

Block A – week 1 to week 30
Block B – week 30 to week 60
Block C – week 60 to week 90

SITE PLANS

DESIGN

PROGRESS REPORT

Please see below progress tables and photos showing progress to Block B (15/07/2019)

PROGRESS GALLERY

Block C elevation 7-11 before crop(2)
IMG_6540 (003)
IMG_6540 (003)
11-03-19 perspective photo
Wellington Elevation
Wellington Elevation
Wellington Elevation
Wellington Elevation
Wellington Elevation
Wellington Elevation 05-10-18 Elevation 1-6 tower
WellingtonCloseBefore-15
WellingtonCloseBefore-15
WellingtonCloseBefore-14
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
WellingtonCloseBefore-17
Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image... Loading image...

CONTACTS

Project Manager

Simon Enticknap

simonenticknap@dbfacades.com

Over-Cladding Supervisor

Ashley Hallett

lkiltd@live.co.uk

Over-Cladding Supervisor

Erl Kitchen

lkiltd@live.co.uk

Tennant Liason Officer

Mercy Mene-Otubu

mercy@dbfacades.com

IMG_0423

Site Manager

Mark Addison

mark@dbfacades.com

If residents have questions or queries please direct them to – mercy@dbfacades.com